Huhtamaki Ronsberg
Huhtamaki
Time of execution: 1997 - 2003
 
Client / operator: Huhtamaki Ronsberg
Central plant of the Huhtamaki Germany Ltd.
Clerk Mr. Richter
Heinrich - Nicolausstraße 6
87671 Ronsberg / Allgäu
GERMANY
Phone: +49 (0)8306 / 77-0
 
Order volume: EMSR-technology approx. 200.000,00 € 
 
Mentruum fuel pump: 90.000 l Ethanol
60.000 l Ethyl acetate
20.000 l Palatinol
10.000 l Ethoxy propanol
10.000 l Isopropyl acetate
10.000 l Acetone
10.000 l N-Propanol
 
Building activity:
  • Implementation of overfill protector and level measurement to display required wait time
    cut-offs and alerting of states of risks.
  • Exchange of liquid- and leak detector to supervise the double-wall mentruum fuel pump.
Our field of activity: Our order volume comprised because of the toughening of the complete tank surveillance system
the following new activities respectively rebuilding activities:
  • Implementation of overfill protectors with WHG, VbF and PTB zone 0 approval
  • Implementation of level measurements with WHG, VbF and PTB zone 0 approval
  • Leak surveillance for cases with flammable liquids of the hazard category
  • Open-air electronic control cabinet 
  • Electronic installation with required high-grade steel constructions
  • Flash and overvoltage protection
  • Charging level supervising
  • Inundation supervising
  • Transmitting and alerting of malfunction
  • Starting-up and functional testing